Stansted Airport

Client: McAlpine

Contract Value:  £3.3m

Services Provided: Installation of 15km 33kV dual circuit cable. 2 circuits of 400mm2 3 x 1core cables between Bishops Stortford Grid and Stansted Airport Primary, plus associated pilot cables.

Scope Included:

  • Single trench, fully ducted installation, 500mm separation between circuits
  • Directional drill beneath railway line (Bentonite filled ducting)
  • Approximately 50:50 carriageway/unmade surface
  • Traffic management
  • Ecology, environmental & archaeological management